|
The objective of the Clean Water Act (CWA) is to
restore and maintain the chemical, physical, and biological
integrity of the Nation’s waters. Toward achievement of this
goal, the CWA prohibits the discharge of dredged or fill
material into waters of the United States unless a permit issued
by the Army Corps of Engineers or approved State under CWA
Section 404 authorizes such a discharge.
For every authorized discharge, the adverse impacts to
wetlands, streams and other aquatic resources must be avoided
and minimized to the extent practicable. For unavoidable
impacts, compensatory mitigation is required to replace
the loss of wetland and aquatic resource functions in the
watershed.
Compensatory mitigation refers to the restoration,
establishment, enhancement, or in certain circumstances
preservation of wetlands, streams or other aquatic resources for
the purpose of offsetting unavoidable adverse impacts.
PERMIT DECISION
Of great importance to the project evaluation is the Corps
public interest balancing process. The public benefits and
detriments of all factors relevant to each case are carefully
evaluated and balanced. Relevant factors may include
conservation, economics, aesthetics, wetlands, cultural values,
navigation, fish and wildlife values, water supply, water
quality, and any other factors judged important to the needs and
welfare of the people. The following general criteria are
considered in evaluating all applications:
- The relevant extent of public and private needs;
- Where unresolved conflicts of resource use exist, the
practicability of using reasonable alternative locations and
methods to accomplish project purposes; and
- The extent and permanence of the beneficial and/or
detrimental effects the proposed project may have on public
and private uses to which the area is suited.
No permit is granted if the proposal is found to be contrary
to the public interest.
Source: USACE Website (http://www.mvn.usace.army.mil/ops/regulatory/permover.asp)
Typical Processing Procedure for a Standard Individual Permit
- Pre-application consultation (optional)
- Applicant submits ENG Form 4345 to district regulatory
office*
- Application received and assigned identification number
- Public notice issued (within 15 days of receiving all
information)
- 30 day comment period depending upon nature of activity
- Proposal is reviewed by Corps** and:
- Public
- Federally Recognized Tribes
- Special interest groups
- Local agencies
- State agencies
- Federal agencies
- Corps considers all comments
- Other Federal agencies consulted, if appropriate
- District engineer may ask applicant to provide
additional information
- Public hearing held, if needed
- District engineer makes decision
- Permit issued
or
Permit denied and applicant advised of reason
*A local variation, often a joint federal-state
application form may be submitted.
** Review period may be extended if applicant fails to submit
information or due to requirements of certain laws.
Source: USACE News Orleans District (http://www.mvn.usace.army.mil/ops/regulatory/permitapply.asp)
|